Inside the Fukushima Line Where CIO's Made-in-Japan USB Charger Is Being Built

Open on YouTube ↗
Overview

The sixth installment of CIO's domestic charger project is a tour of the production line at Asahi Electronics, an EMS (electronics manufacturing services) company in Fukushima Prefecture. On the day of filming, Asahi Electronics had just completed a small-volume pre-production run. According to the CIO representative, if the overall process shows no issues, the project moves into full-scale mass production. Earlier prototypes had already been mass-produced in China, so the tour compares the two approaches: how the Japanese line is organized, what it adds, and how much it can produce.

11 min read
1:02

Cell Production Instead of a Conveyor Belt

The CIO representative explains that the Japanese line uses the cell production method. In China, the product moved along a conveyor belt and units came off the line one after another. At Asahi Electronics, the floor is divided into cells, small booths that each handle a specific process, such as kitting. Workers stand at a cell and do that stage of the work, then pass the unit to the next cell. In the end it still works like a flow line, but each cell owns one process.

The representative presents this as a matter of flexibility. A conveyor line has to be fully set up in advance, with everyone ready at once and a fixed number of people assigned. With cells, a few people can run the process, which suits small-volume production. If more people are available, they can be spread across the sections to increase output. The representative also acknowledges that a conveyor line is generally more efficient for running the whole process at volume. Cell production can be scaled up, for example by preparing twice as many cells, but output is largely bounded by the floor area set aside for it.

On volume, the representative says a conveyor line might produce 1,000 to 2,000 units a day or more, depending on how hard the product is to make. For the space arranged at Asahi Electronics, they estimate a daily ceiling of roughly 500 to 700 units. The interviewer suggests that works out to about 10,000 a month, and the representative agrees.

3:35

Kitting and the Traceability System

Kitting is the first step. Asahi Electronics assembles three main components: the circuit board (the core of the charger), the product case, and the TFT display. The kitting cell unpacks the parts and checks that everything needed for that day's run is actually present before work proceeds. The trial run covered a few dozen units.

The interviewer notices barcode-scanner-like devices that they did not see on the Chinese line. The representative explains that these belong to a traceability system. Each circuit board has a QR code printed on its underside, and QR codes are also attached to the product cases. The QR codes are scanned and the units registered in the system as they move through production.

4:59

Incoming Inspection of the TFT Display

The next station holds a jig, also built by Asahi Electronics, for checking that the TFT LCD displays correctly. The TFT is shipped in separately from the other parts, so the line confirms it works when it is received, before it moves to assembly. The representative says Asahi Electronics proposed this incoming-inspection step and the jig.

The reasoning is about waste. If a broken TFT is only discovered after assembly, the work done up to that point is lost, both labor and cost, and a fair number of parts may have to be discarded. Checking components while they are still separate avoids that loss.

6:08

ATE Testing and Mounting the Board in the Case

An ATE (automated test equipment) station then turns on the TFT and checks automatically that power flows correctly at the circuit-board level. Units that pass move on. The interviewer remarks that this stage looks almost the same as what they saw in China.

The board is then installed in its case, which creates a traceability problem. Once the board is inside, its QR code can no longer be read. The fix is to print a separate QR code label and stick it on the product. The worker scans this new code together with the code for that product's circuit board, so the two are linked, and the unit continues down the line.

7:14

Potting Compound: Weighing, Tolerances, and Planned Automation

At the potting station there is a scale, and the potting compound is applied while being weighed. The representative explains that uneven filling inevitably affects heat dissipation. For this product, the target range is 5 to 7 grams. Above 7 grams, the compound leaks out, and the interviewer adds that oozing silicone would spoil the appearance. Below the range, heat does not transfer properly.

The representative says this is a stage where results vary from worker to worker. Judging by eye or relying on experience lets inconsistencies creep in. So after injection, each unit is weighed again to confirm it falls within tolerance before it moves on. Asahi Electronics has proposed a further improvement. Since the compound dispenses at a consistent rate, they plan to time how many seconds it takes to reach the target weight and automate dispensing with a timer. The representative describes this as still in progress, one of several improvements being made as the line develops.

8:31

Ultrasonic Welding and On-Site Firmware Updates

The case is closed by ultrasonic welding, which the interviewer again says looks similar to the Chinese line. The unit is then a finished product, and its next stop is aging.

Before that, the interviewer points out a station that appears to handle firmware updates. The representative explains the reason for it. If specifications change partway through production, sending units back to China to reflash the firmware would take a lot of time. Because assembly from this point happens in Japan, they prepared a firmware-update jig so that changes can be handled domestically. The interviewer sums it up: the first firmware version is written in China, and later updates can be applied in Japan if specifications change. The representative broadly agrees.

9:47

Where the Aging Process Will Go

The spot right after the firmware station, where aging would normally happen, is empty. The representative says this was partly a matter of time. Installing the aging equipment there for pre-production would have required wiring and other work, so for now it stays on the first floor. Units are checked there, including power-on tests, and then carried back upstairs.

The interviewer asks whether running it this way in real mass production would create a bottleneck. The representative says they are in the final stages of discussing placement, and the equipment will probably end up in that spot. The interviewer notes that power cables already come down from the ceiling there.

The Aging Test and a 3-in-1,000 Benchmark

On the first floor, the aging machine looks much like the one in China. The units are wired with CIO's own cables. Each unit is connected and run continuously for about four hours. The representative explains that many units need thorough testing, and that problems may only appear after long operation under heavy strain. So the test runs long-term under full, high-load conditions.

After the test, they count defective units against the number tested. The representative gives roughly 3 per 1,000 as their passing benchmark. If the rate is higher, they identify the causes and review the production process for problems. The representative frames this as a checkpoint on the way to improvement.

In passing, the interviewer notices adhesive tape for removing dust and dirt from clothing, and mentions that they wore the required clothing and cap during the visit.

11:53

Dielectric Strength Test and a Second ATE Pass

After aging comes a dielectric strength (withstand voltage) test. The representative describes it as checking how the product handles overvoltage at various points, for example from a short circuit or a lightning strike. The unit then goes through ATE once more for re-verification before the user-oriented tests begin.

User-Scenario Tests Still Being Finalized

The last section of the line is visibly unfinished. The representative says the specifications here are not yet settled, and they are finalizing, with Asahi Electronics, exactly what equipment to install and how to run the tests.

  • Coil whine test. A load is applied to check for the high-pitched noise characteristic of chargers. Because the area is an open space, sound can leak and be hard to hear. They are still working out how to keep the test environment quiet enough.
  • Live device test. This differs from simply applying power with ATE. It checks that the charger actually charges real devices the way customers will use them. The main targets are iPhone and Android phones, with PCs also mentioned, since many computers now charge over USB and the charger supports 65W.
  • Bluetooth test. The charger is placed in a box that blocks radio signals. The test checks whether it pairs, whether the screen in the app changes, and whether settings take effect. The representative says the goal is to recreate how real users use the product.
  • Rattle check. At the very end, the finished charger is shaken or tapped repeatedly to listen for rattling. Poor assembly can leave parts loose, so this serves as the final safeguard against physical problems.
14:34

Packing

Packing also follows the cell approach, with items handled one by one. The representative contrasts this with China, where tasks such as blister packing might be split among different workers. At Asahi Electronics, one person puts all the set items into the package, and a reviewer checks and finalizes it. The representative expects this stage to run in a somewhat condensed form as well.

15:19

What Remains Before Mass Production

In closing, the interviewer lists the main changes from the Chinese line: the move to cell production and the ability to trace individual units. The CIO representative says the project has reached the final stage before products reach customers, and full-scale mass production is set to begin in a few weeks. They acknowledge that some parts of the line, as the tour showed, are not yet fully addressed. These include the final placement of the aging equipment, the potting automation, and the specifications for the user-scenario tests. The representative says they plan to visit Asahi Electronics almost every week to work through these issues in parallel. They also note that the Makuake crowdfunding campaign is still running.